Future Homes Standard transitional arrangements: what they mean for your project timeline

The Future Homes Standard regulations come into force in England on 24 March 2027. A project can stay under the current Part L rules if its building notice, initial notice or full plans application is given before 24 March 2027 and work on that building starts before 24 March 2028.

A new-build UK house under construction as solar panels are fitted to its roof

Grassendale Ecohouse · 16 November 2026

The key dates

The government published the Future Homes and Buildings Standards building circular on 24 March 2026. It sets out three dates that matter for most new homes:

DateWhat happens
24 March 2026Circular and new Approved Document L published
24 March 2027The regulations come into force for most building work
24 March 2028Last date to start work on a building and keep the old rules under the transitional arrangements

Higher-risk buildings follow a different timetable: the main regulations apply to higher-risk building work from 24 September 2027, and the transitional protection depends on a valid building control approval application reaching the regulator before that date.

How the transitional arrangements work

For work that isn't higher-risk building work, the circular says the new requirements don't apply where a building notice, initial notice or full plans application was given before 24 March 2027, as long as the work it relates to is started on that building before 24 March 2028.

Two things follow from that:

  1. Getting your building control application in before 24 March 2027 is not enough on its own. Each building has to be started before 24 March 2028.
  2. On a phased site, buildings that aren't started by 24 March 2028 fall under the new standard, even if the application covered them.

What the new standard adds

The circular creates a new functional requirement, L3, for on-site renewable electricity generation on new dwellings and buildings containing dwellings. Its stated aim is homes built with low carbon heating and high levels of energy efficiency.

What to do now

  1. List every building on your project and the date work will start on each one.
  2. If any start date falls after 24 March 2028, design those buildings to the new standard now rather than redesigning later.
  3. Get your building control application in before 24 March 2027 if you want to rely on the transitional arrangements.
  4. Ask for SAP calculations early, so the energy design is settled before you commit to a specification.

If you'd like help working out which rules apply to your scheme, our SAP calculations service covers design-stage and as-built assessments, and you can contact us to talk it through.